The Campus Center Has A New Nest!
Phase Two of the Campus Center Renovation Project is complete, and the upgrades are receiving rave reviews from students.
The Nest is the highlight of the renovation, with its modern lounge design, seating that is more attractive to students, and a wider variety of food options based on student surveys and feedback.
Food selections include more vegan/vegetarian menu items, an expanded salad bar, and made to-order options at every meal. One of the stations is free of the nine most common food allergens keeping food separate from storage to cooking and serving.
Phase Two Construction Stats:
- Start date > May 20, 2024
- Substantial completion date > Jan. 27, 2025
- Hours worked > Over 27,000.
- Workers > 251 construction workers and 29 trade partners.
- Waste disposal > 29.31 tons of waste hauled; 24 tons of waste recycled.
- Renovation area > 15,346 square feet.
- Addition area > 1,200 square feet.




We would like to extend our special thanks to our valued donors who made this project possible.